Overnight Work in Auburndale Square

In order to complete paving of Auburndale Square, the Department of Public Works will be utilizing the following schedule:

Milling: OVERNIGHT WORK (8pm-5am)

Sunday, July 9th

Monday, July 10th

Tuesday, July 11th (if needed)


Pre for paving: DAYTIME WORK

Monday, July 10th-Thursday, July 13th


Base paving: OVERNIGHT WORK (8pm-5am)

Sunday, July 16th

Monday, July 17th

Tuesday, July 18th (if needed)


Final paving: OVERNIGHT WORK (8pm-5am)

Sunday, July 23rd

Monday, July 24th

Tuesday, July 25th (if needed)


Please note that this schedule it subject to change depending on weather. We apologize for any inconvenience that this may cause. If you have any questions or concerns, please contact DPWprojects@newtonma.gov

Thank you.