Construction is underway for traffic signalization and safety improvements at two intersections: Dedham Street @ Nahanton Street and Dedham Street @Brookline Street and Carlson Avenue. Both intersections are crash hot spots, ranked by MassDOT as among of the top 5% worst crash locations in the region. Improvements include: Geometry modifications, lane and signal modifications , resurfacing, new pavement markings and signage.

Concept Presentation, February 1, 2017

Presentation, March 28, 2017

Construction Updates, November 26, 2017

 

 